In this guide, we will show you how to Fix a Budget in Cost Centre Allocation.
Access: The minimum permissions required to complete the Cost Centre Allocation are found in the Finance Module of Config>Setup>Roles & Permissions.
![](https://d3kchveacp7yrb.cloudfront.net/2023/09/w3P5dNiE-Permissions-Cost-Centre-Allocation-1426x1024.png)
Pre-requisites: In order to Fix the Cost Centre Allocation the Budget must be entered and agreed with the Approved Budget.
Related Guides:
- How to Allocate a Budget in Cost Centre Allocation
- How to Import a Budget into Cost Centre Allocation
To begin, go to Module>Finance>Budgeting>Cost Centre Allocation
![](https://d3kchveacp7yrb.cloudfront.net/2023/09/aRu0ZerJ-Cost-Centre-Allocation-Pathway-688x1024.png)
Select the Budget Scenario from the drop down that you wish to fix.
![](https://d3kchveacp7yrb.cloudfront.net/2023/09/fCcNbloP-Cost-Centre-Allocation-Scenario.png)
Review the data in the Cost Centre Allocation.
![](https://d3kchveacp7yrb.cloudfront.net/2023/09/image-1029x1024.png)
Once you are happy the values agree with your Approved Budget click Fix Budget.
![](https://d3kchveacp7yrb.cloudfront.net/2023/09/Cost-Centre-Allocation-Fix.png)